Friday, September 24, 2010


The contractor constructed the decorative median on Waukegan between Overlook Drive and Golf Road this week. The contractor will continue completing landscaping work and other miscellaneous concrete work this week and into next week.

The contractor for the IDOT Resurfacing project continues with asphalt surface grinding and curb and gutter removal for replacement.

Friday, September 17, 2010

Phase I work, the concrete medians and curb bump outs has been completed. The contractor will be completing miscellaneous concrete work (curbs and sidewalks) and landscaping this week.

The contractor for the IDOT Resurfacing project has started asphalt surface grinding and continues with curb and gutter removal for replacement.

Friday, September 10, 2010

Phase I work, the concrete medians and curb bump outs has been completed this week. The contractor will be completing miscellaneous concrete work (curbs and sidewalks) and landscaping over the next week. The contractor for the IDOT Resurfacing project has started curb and gutter removal for replacement prior to resurfacing Waukegan Road.

Thursday, September 2, 2010

Phase I work, the concrete medians and curb bump outs will be completed this week.

The contractor for the IDOT Resurfacing has begun curb & gutter removal and replacement before the resurfacing of the road can commence.

Friday, August 27, 2010

The concrete contractor is still onsite, but is nearing completion of concrete work! You may notice the new medians at the intersection of Glenview Road and Waukegan Road are in, which means there isn't much left of Phase I!

Additionally, the contractor for the IDOT Resurfacing has arrived onsite to begin utility structure adjustments prior to resurfacing Waukegan Road.

Friday, August 20, 2010

The Village portion of the project, which includes the concrete curb bump-outs and medians is nearing completion. The contractor just has a few areas remaining, including a new median at the intersection of Glenview Road.

The contractor for the IDOT Resurfacing has rescheduled the structure adjustments along Waukegan for next week.

Friday, August 13, 2010

Copenhaver, the contractor for the Enhancements Projects, has been working hard to finish the curb bump outs and concrete medians. They have about a week’s worth of work remaining on the items directly adjacent to Waukegan Road. Once they finish those items, they will start on the work behind the curb and aprons.

Plote, the contractor for the Resurfacing Project, should be onsite this week making adjustments to the sewer structures that are in the road. They will be starting the removal of the top 2” of road soon. Please allow extra travel time if you’re going to be using Waukegan Road!