The contractor will continue completing landscaping work and other miscellaneous asphalt and concrete work next week. The contractor is scheduled to construct the decorative crosswalk at Kraft Court late next week.
The contractor for the IDOT Resurfacing project is scheduled to pave the hot-mix asphalt leveling binder next week.
Friday, October 8, 2010
Friday, October 1, 2010
Friday, September 24, 2010

The contractor constructed the decorative median on Waukegan between Overlook Drive and Golf Road this week. The contractor will continue completing landscaping work and other miscellaneous concrete work this week and into next week.
The contractor for the IDOT Resurfacing project continues with asphalt surface grinding and curb and gutter removal for replacement.
Friday, September 17, 2010
Phase I work, the concrete medians and curb bump outs has been completed. The contractor will be completing miscellaneous concrete work (curbs and sidewalks) and landscaping this week.
The contractor for the IDOT Resurfacing project has started asphalt surface grinding and continues with curb and gutter removal for replacement.
The contractor for the IDOT Resurfacing project has started asphalt surface grinding and continues with curb and gutter removal for replacement.
Friday, September 10, 2010
Phase I work, the concrete medians and curb bump outs has been completed this week. The contractor will be completing miscellaneous concrete work (curbs and sidewalks) and landscaping over the next week. The contractor for the IDOT Resurfacing project has started curb and gutter removal for replacement prior to resurfacing Waukegan Road.
Thursday, September 2, 2010
Friday, August 27, 2010
The concrete contractor is still onsite, but is nearing completion of concrete work! You may notice the new medians at the intersection of Glenview Road and Waukegan Road are in, which means there isn't much left of Phase I!
Additionally, the contractor for the IDOT Resurfacing has arrived onsite to begin utility structure adjustments prior to resurfacing Waukegan Road.
Additionally, the contractor for the IDOT Resurfacing has arrived onsite to begin utility structure adjustments prior to resurfacing Waukegan Road.