The concrete contractor is still onsite, but is nearing completion of concrete work! You may notice the new medians at the intersection of Glenview Road and Waukegan Road are in, which means there isn't much left of Phase I!
Additionally, the contractor for the IDOT Resurfacing has arrived onsite to begin utility structure adjustments prior to resurfacing Waukegan Road.
Friday, August 27, 2010
Friday, August 20, 2010
The Village portion of the project, which includes the concrete curb bump-outs and medians is nearing completion. The contractor just has a few areas remaining, including a new median at the intersection of Glenview Road.
The contractor for the IDOT Resurfacing has rescheduled the structure adjustments along Waukegan for next week.
The contractor for the IDOT Resurfacing has rescheduled the structure adjustments along Waukegan for next week.
Friday, August 13, 2010
Copenhaver, the contractor for the Enhancements Projects, has been working hard to finish the curb bump outs and concrete medians. They have about a week’s worth of work remaining on the items directly adjacent to Waukegan Road. Once they finish those items, they will start on the work behind the curb and aprons.
Plote, the contractor for the Resurfacing Project, should be onsite this week making adjustments to the sewer structures that are in the road. They will be starting the removal of the top 2” of road soon. Please allow extra travel time if you’re going to be using Waukegan Road!
Plote, the contractor for the Resurfacing Project, should be onsite this week making adjustments to the sewer structures that are in the road. They will be starting the removal of the top 2” of road soon. Please allow extra travel time if you’re going to be using Waukegan Road!
Friday, July 30, 2010
Friday, July 23, 2010
STRIKE HAS BEEN RESOLVED, CONSTRUCTION RESUMES!
The strike was resolved this week and new contracts between the unions and contractors have been signed and are in effect. The contractor resumed work this week!
The contractor has resumed work on the center concrete median on the south portion of the project, near Golf Road.
The contractor has resumed work on the center concrete median on the south portion of the project, near Golf Road.
Tuesday, July 13, 2010
Strike Continues
As of this morning, the strike continues. The Unions and the Contracting Companies are still in negotiations and have not yet reached an agreement. It is our understanding that the next scheduled meeting is set for Monday, July 19.
We continue to ask for your patience and understanding during this time. We are continuing to monitor each construction site so that they remain safe to the general public.
As stated below, please do not hesitate to contact the Village Project Manager or the Capital Projects Department at (847) 998-9500.
We continue to ask for your patience and understanding during this time. We are continuing to monitor each construction site so that they remain safe to the general public.
As stated below, please do not hesitate to contact the Village Project Manager or the Capital Projects Department at (847) 998-9500.
Thursday, July 1, 2010
STRIKE NOTICE
Dear Resident:
Thank you for your ongoing patience during the Village construction project adjacent to your home. At this time, the Village has been notified that Chicagoland Construction Labor Unions are going on strike. The conflict is between the Contracting Companies and the Unions, not involving the Village.
Work has therefore been temporarily shut down on your street. We are insuring that all construction sites are safe to the general public and will continue to actively monitor each site.
If any issues arise, or if you should have any questions, please contact the Village Project Manager or the Capital Projects Department at (847) 998-9500.
As of today, we do not have any information on how long this strike could last. We will inform you when this issue is resolved and work will resume.
Thank you again for your patience while this matter is resolved.
Thank you for your ongoing patience during the Village construction project adjacent to your home. At this time, the Village has been notified that Chicagoland Construction Labor Unions are going on strike. The conflict is between the Contracting Companies and the Unions, not involving the Village.
Work has therefore been temporarily shut down on your street. We are insuring that all construction sites are safe to the general public and will continue to actively monitor each site.
If any issues arise, or if you should have any questions, please contact the Village Project Manager or the Capital Projects Department at (847) 998-9500.
As of today, we do not have any information on how long this strike could last. We will inform you when this issue is resolved and work will resume.
Thank you again for your patience while this matter is resolved.