Friday, July 29, 2011

Copenhaver Construction is working to complete punch list work along Waukegan Road corridor by early next week.

Friday, July 22, 2011

Copenhaver Construction has completed a majority of the punch list work along the Waukegan Road corridor this week and looks to complete the project this month.

Friday, July 15, 2011

Copenhaver Construction has completed a majority of the punch list work along the Waukegan Road corridor this week and looks to complete the project this month.

Friday, July 8, 2011

Copenhaver Construction has completed a majority of the punch list work along the Waukegan Road corridor this week and looks to complete the project this month.

Thursday, June 30, 2011

Copenhaver Construction has completed a majority of the punch list work along the Waukegan Road corridor this week and looks to complete the project next week.

Friday, June 24, 2011

Copenhaver Construction has completed a majority of the punch list work along the Waukegan Road corridor this week and looks to complete the project next week.

Thursday, June 16, 2011

Lyons-Pinner Electric has completed the replacement of detector loops at the intersection of Glenview Road and Waukegan Road this week. Copenhaver Construction has completed a majority of the punch list work along the Waukegan Road corridor this week and looks to complete the project next week.