Friday, August 27, 2010

The concrete contractor is still onsite, but is nearing completion of concrete work! You may notice the new medians at the intersection of Glenview Road and Waukegan Road are in, which means there isn't much left of Phase I!

Additionally, the contractor for the IDOT Resurfacing has arrived onsite to begin utility structure adjustments prior to resurfacing Waukegan Road.

Friday, August 20, 2010

The Village portion of the project, which includes the concrete curb bump-outs and medians is nearing completion. The contractor just has a few areas remaining, including a new median at the intersection of Glenview Road.

The contractor for the IDOT Resurfacing has rescheduled the structure adjustments along Waukegan for next week.

Friday, August 13, 2010

Copenhaver, the contractor for the Enhancements Projects, has been working hard to finish the curb bump outs and concrete medians. They have about a week’s worth of work remaining on the items directly adjacent to Waukegan Road. Once they finish those items, they will start on the work behind the curb and aprons.

Plote, the contractor for the Resurfacing Project, should be onsite this week making adjustments to the sewer structures that are in the road. They will be starting the removal of the top 2” of road soon. Please allow extra travel time if you’re going to be using Waukegan Road!