Friday, October 22, 2010

The contractor will continue completing landscaping work and other miscellaneous asphalt and concrete work next week.

The contractor is scheduled to construct the decorative crosswalks at Waukegan Road and Overlook Drive early next week. Overlook Drive will be closed for approximately one (1) week. Motorists will need to use the signed detour for Overlook Drive.

The contractor is scheduled (weather permitting) to construct the decorative crosswalks at Waukegan Road and Dewes Street late next week.

The contractor for the IDOT Resurfacing project is scheduled to complete the hot-mix asphalt paving next week, with landscaping and restoration work to commence shortly thereafter.

Friday, October 15, 2010

The contractor is constructing the decorative crosswalk at Kraft Court this week. The contractor will continue completing landscaping work and other miscellaneous asphalt and concrete work next week.

The contractor is scheduled to construct the decorative crosswalk at Overlook Drive late next week.

The contractor for the IDOT Resurfacing project is scheduled to pave the hot-mix asphalt surface course next week.

Friday, October 8, 2010

The contractor will continue completing landscaping work and other miscellaneous asphalt and concrete work next week. The contractor is scheduled to construct the decorative crosswalk at Kraft Court late next week.

The contractor for the IDOT Resurfacing project is scheduled to pave the hot-mix asphalt leveling binder next week.

Friday, October 1, 2010

The contractor will continue completing landscaping work and other miscellaneous concrete work this week and into next week.

The contractor for the IDOT Resurfacing project continues with curb and gutter removal and replacement and hot-mix asphalt pavement patching.